Golisano Children's Hospital: By the numbers

Rochester Business Journal
May 22, 2015

Number of floors: 8

Total square feet: 245,000

Project cost: $145.9 million for first phase, $191.2 million total 

Daily workers: Approximately 200

Tons of steel: 2,588 tons

Piles driven: 375

Concrete poured: 10,000 cubic yards

Bricks placed: 400,000

Exterior glass: 33,000 square feet

Interior glass: 12,000 square feet

Fiber-reinforced cement panels: 23,000 square feet

Dry wall: 1,000,000 square feet

Ceiling grid: 100,000 square feet

Ceiling tile: 25,000 pieces

Pounds of ductwork: 567,772

Length of ductwork: 24,210 feet (4.6 miles)

Length of copper piping: 85,000 feet (16 miles)

Philanthropic gifts: Nearly 8,500 individuals and community groups—from 38 states, the District of Columbia, and two Canadian provinces—have given more than $53 million to date

Air handlers: 4—each unit could heat/cool 48 average-sized homes

Emergency generators: 3

Philanthropy: One-third of donors, many of whom are children themselves, to the new Golisano Children’s Hospital have given $25 or less.

5/22/15 (c) 2015 Rochester Business Journal. To obtain permission to reprint this article, call 585-546-8303 or email service@rbj.net.


What You're Saying 

There are no comments yet. Be the first to add yours!

Post Your Own Comment

 
Username:
Password:

Not registered? Sign up now!
 

To Do   Text Size
Post CommentPost A Comment eMail Size1
View CommentsView All Comments PrintPrint Size2
ReprintsReprints Size3
  • E-mailed
  • Commented
  • Viewed
RBJ   Google